A Renovation Schedule

I hesitate to put any of this down on paper, since everything seems to take longer than expected, but I'm really looking forward to things coming together very soon:

Aug 11: Finish downstairs walls, plumbers finish the plumbing
Aug 12: Pulling carpet staples, carpet tack nails, and screws from hardwood floors.
Aug 13-18: Downstairs hardwood floors get professionally refinished
August 17-25: Build, upstairs foyer arch, walls go up in upstairs, tile master bath shower.
Aug 19-25: Polyurethane dries and hardens on floors downstairs, can't walk on them.
September 1: Kitchen cabinets are delivered
September 1-5: Kitchen is installed, appliances are delivered
September 26: Kitchen countertops are installed

There is light at the end of the tunnel!